This article describes specifics for the TI AWR2944EVM evaluation board.

Preparing for J-Link

  • Connect the J-Link with the SEGGER MIPI-60 adapter to the 60-pin J19 header (MIPI_CONN) on the board.
  • Relevant switch / jumper settings:
Switch / Jumper Setting
S1.1 (JTAG_MUX) MIPI
J17 (SOP2) Open
J18 (SOP1) Open
J20 (SOP0) Closed
  • Power the board with 12V via J12 jack connector